MARINE PARK WATER RECLAMATION FACILITY - Operations and Maintenance Manual

<-- Previous Section
Home

Next Section -->
 

Section 20 - Grit Removal

20.01General Overview
20.02Design Criteria
20.03Computer Assisted Control Strategies
20.04Operating Strategies
20.05Troubleshooting
20.06Safety
20.07Records/Sampling


20.01 General Overview

The purpose of providing grit removal is to protect downstream mechanical devices from accelerated wear due to abrasion. In addition, hydrogen sulfide will be stripped from the waste water which is ventilated to the air treatment system.

The aerated grit chambers are designed to be constructed in three phases. During Phase I, two grit chambers with a central grit pumping gallery were constructed. In Phase II, two additional chambers were constructed however, only one of the two chambers was equipped for operation. In Phase III, the final chamber will receive the pumps and other equipment necessary for operation. Each grit chamber is 45 feet long, 10 feet wide and 10 feet deep, and has three grit bays to collect the settled grit. The flow is introduced into the chamber at right angles to the chamber length to impart a spiral flow pattern. The grit chambers have coarse bubble diffusers located above the grit bays which will induce a vertical roll into the waste water perpendicular to the general flow pattern. Positive displacement blowers supply air to the diffusers. The velocity of the roll governs the particle size of a specific gravity that will be removed. By adjusting the airflow supplied by the blower(s), it will be possible to cause the grit to settle and keep the organic material in suspension. During periods of low influent flow, hydrogen sulfide will be stripped from the wastewater by aeration.

The settled grit collected in the grit bays is removed from the chamber with grit pumps, one for each bay. The grit pumps for each chamber pump the grit slurry to two cyclone degritters. Through centrifugal force, the cyclones separate the heavier particles of grit and solids from the bulk of the liquid. The underflow from the degritters is then discharged to a grit classifier, which washes and separates any remaining organic material contained in the grit. The liquid from the degritters and classifiers is returned to the wastewater upstream of the grit chambers.

Specific design features of the grit chambers include:

With one of the three chambers out of service, the peak flow detention time equals 2.5 minutes. At the design year with three of four units in service, the peak hour flow detention time will also equal 2.5 minutes. One of the two blowers provides the required airflow, and ultimately both grit chamber aeration blowers will provide the required airflow. In the case of a blower failure, additional air can be supplied by redirecting air from a channel aeration blower to the grit chambers. Each chamber has three grit pumps pumping to two cyclones. The grit pump for the first bay will be dedicated to one cyclone and the grit pumps for the second and third bays will alternately discharge to the other cyclone.

20.02 Design Criteria

The design criteria for the Grit Removal System Phase II are presented below.

AERATED GRIT CHAMBERS
Number of Units
     Initial2
     Phase II3
     Ultimate4
Volume, Each4898 CF
Detention Time (Peak Hour Flow)
     Initial (2 Units)5.1 Min.
     Phase II4.2 Min.
     Ultimate (4 Units)3.4 Min.
Grit Bays/Grit Chamber3
 
GRIT CHAMBER BLOWERS
     Initial2
     Ultimate2
Capacity530 SCFM
TypePositive Displacement
 
DIFFUSERS
Number/Grit Chamber24
TypeCoarse Bubble
 
GRIT PUMPS
     Initial6
     Phase II9
     Ultimate12
Capacity220 GPM
TypeRecessed Impeller Centrifugal
 
GRIT CYCLONES
     Initial4
     Phase II6
     Ultimate8
Capacity220 GPM @ 5 PSIG
Underflow15 GPM
 
GRIT CLASSIFIERS
Number of Units
     Initial2
     Phase II3
     Ultimate4
TypeInclined Screw
Size18" Full Flare
Capacity (150 Mesh)52 GPM

20.03 Computer Assisted Control Strategies

20.03.a. General Overview

The Marine Park Facility has available three grit chambers, with a total of four chambers planned after Phase III is completed. The operator will select one, two or three chambers to be on line. The grit removal system consists of:

Raw wastewater enters one or more grit chambers that provide up to 2.5 minutes of detention time. As grit settles out it is withdrawn from the grit chambers by the nine grit pumps. If desired, air is injected into the "grit sump " to prevent plugging of the pump. Grit is pumped to one of the six cyclone degritters, where heavier material is removed. The degritted water is returned to the headworks. The grit is then classified by one or more grit classifier(s) prior to discharge into a rolloff dumpster for final disposal.

20.03.b. Control Strategies

This section tells the operator how to interact with the SCS to control the grit system. It describes each control loop, and how and where equipment status and alarm indicators function.

20.03.b.1. Grit Chambers Combustible Gas Monitoring

Loop Function:Monitors the screened influent for dangerous concentrations of explosive gases.

Monitors air flow to each grit chamber.
Instrumentation:FI-04051, FI-04052, FI-04253(Flow indicators) Located on each chamber air supply header.
Alarms:AIT/AE-04041, AIT/AE-04042, AIT/AE-04243(LEL combustible gas sensor) Located at each chamber.
Note: Only chamber #3 has an operable system.
PLC/SCS Function:Monitors grit chambers for dangerous concentrations of explosive gases (AIT/AE-04041, AIT/AE-04042, AIT/AE-04243)

Operation:

  1. A gas sensor in each grit chamber continuously monitors for the presence of combustible gases. When the level of combustible gases reaches the alarm level as set on the alarm module located on LCP-01, the alarm beacon and alarm horn are activated. Pressing the horn silence button silences the alarm horn. The alarm condition is also monitored by the PLC/SCS system. The alarm condition is reset at the alarm module. When the level of combustible gas reaches the warning level as set on the alarm module, an input to the PLC is activated to notify the operator of the conditions through the SCS. Alarms also trigger the autodialer system as described elsewhere.

20.03.b.2. Grit Blowers

Loop Function:Monitors the blower(s) ON status.

Monitors the HOR handswitch position, and determines if a blower fails.

Provides for blower auto sequencing.
Instrumentation:QL-05051, QL-05052 (OOR), Blower ON status

QL-05051, QL-05052 (HOR), Monitors handswitch REMOTE position
Alarms:QA-05051, QA-05052, (RUN, FAIL)
Determines blower run fail in REMOTE position, and provides alarm
PLC/SCS Function:Monitors the blowers in operation. Provides alarm in the event of blower failure. Provides blower sequencing.

Operation:

  1. One of two grit blowers is placed in REMOTE position (after first checking that discharge valves are open). Whichever blower is placed in REMOTE position first becomes the lead blower, with the second blower functioning as the standby blower should the lead blower fail. A Lead Select button on the Low Pressure Blower SCADA screen allows the operator to alternate lead blowers as necessary. Selecting a new lead blower initiates a countdown timer, which delays the stopping of the previous lead blower for 30 seconds. The SCS monitors which blower is on line and informs the operator in the event of a failure.

20.03.b.3. Grit Pumps

Loop Function:Monitors pump ON status.
Monitors HOR handswitch REMOTE position
Provides pump sequencing
Instrumentation:QL-04011, QL-04012, QL-04013, QL-04021, QL-04022, QL-04023, QL-04231, QL-04233, QL-04233. Monitors pump on status (OOR).

QL-04011, QL-04012, QL-04013, QL-04021, QL-04022, QL-04023, QL-04231, QL-04233, QL-04233 Monitors HOR handswitch (OOR).
Alarms:QA-04011, QA-04012, QA-04013, QA-04021, QA-04022, QA-04023, QA-04231, QA-04233, QA-04233. Determines pump run/fail in REMOTE and provide alarm (RUN FAIL).
PLC/SCS Function:Monitors which pump(s) are on. Monitors pump(s) in REMOTE status, and provides alarm in the event of failure.

Operation:

  1. When in remote, the pump connected to the first grit bay operates continuously. The other two pumps connected to the second and third bays are controlled by a recycle timer with an adjustable ON/OFF setpoint.

20.03.b.4. Grit Classifiers

Loop Function:Monitors classifier ON status
Monitors HOR handswitch in REMOTE position
Provides classifier sequencing
Instrumentation:QL-03011, QL-03012. Monitors classifier ON status (OOR).

QL-03011, QL-03012. Monitors handswitch in REMOTE position (OOR).
Alarms:QA-03011, QA-03012. Determines classifier run/fail in REMOTE and provides alarm (RUN FAIL).
PLC/SCS Functions:Monitors which classifier is on. Monitors which classifier is in the REMOTE position, and provides alarm in the event of failure.

Operation:

  1. When in REMOTE position, the classifier is started when the grit pump is discharging to it turns on. When the grit pump turns off, the classifier will continue to run for a set time delay.

20.04 Operating Strategies

20.04.a. General Operating Strategy

The first blower placed in REMOTE mode will function as the LEAD and start immediately, the second blower placed in remote functions as a standby and will come on should the first blower fail. The LEAD blower may be changed by operations through the SCS CRT.

When in REMOTE, the pump connected to the first grit bay operates continuously. The other two pumps connected to the second and third grit bays are controlled by an alternator and a re-cycle timer with an adjustable ON/OFF setpoint.

When selected to REMOTE, the conveyor is started after a set time delay following initiation of a bar screen cleaning cycle. It continues to operate after the bar screen stops for a set time delay. The setpoints and progress of both the on delay and off delay timers can be viewed through the SCS CRTs.

When in REMOTE, the classifier is started when the grit pump discharging to it turns on. When the grit pump turns off, the classifier will continue to run for a set time delay.

The air flow rate to each chamber and each diffuser assembly is manually adjustable to provide uniform aeration of the waste water.

A gas sensor in the grit chamber (#3 only) continuously monitors for the presence of combustible gases. When the level of combustible gases reaches the alarm level as set on the alarm module located on LCP-01, the alarm beacon and alarm horn are activated. The alarm horn is silenced by pressing the horn silence button. The alarm condition is also monitored by the PLC/SCS system. The alarm condition is reset at the alarm module. When the level of combustible gas reaches the warning level as set on the alarm module, an input to the PLC is activated to notify the operator of the conditions through the SCS.

20.04.b. Normal Operating Conditions

Note: Normal plant operations will use the PLC and the SCS CRT to select equipment operating modes, and monitor equipment status. Air flow rate, as mentioned above, is manually adjusted at the air diffuser headers.

20.04.b.1. Grit Chambers (Also see Section 20.03.b.1.)

The grit chambers (#3 only) are continually monitored by the Combustible Gas Sensor, and will activate a local alarm in the event the preset level of hazardous gas is exceeded. In turn, the PLC will activate an alarm through the SCS CRT to notify the operator.

Air flow to the grit chambers is adjusted manually by the operator to facilitate settling out of particles with high specific gravity. Since the grit chambers are covered hydrogen sulfide gas stripped from the wastewater is removed through the odor scrubber system.

EQUIPMENT STATUS TABLE 20.04.b.1.
Equipment DescriptionStatus
Air diffuser header valvesOpen as needed to all grit sumps
FI-04051, FI-04052Air flow indicator valves open
AIT/AE-04041, AIT/AE-04042,AIT/AE-04243LEL Combustible Gas Sensor activated


20.04.b.2. Grit Blowers (also see Section 20.03.b.2.)

The grit blowers are placed in REMOTE position (with the discharge valves open). Blower operation is continually monitored by the PLC, and will send an alarm to the SCS CRT in the event of failure. The PLC will also start the other blower in the event of a failure of the LEAD blower.

EQUIPMENT STATUS TABLE 20.04.b.2.
Equipment DescriptionStatus
Grit Blower #1HOR Handswitch to REMOTE
Grit Blower #2HOR Handswitch to REMOTE
Grit blower suction valveOpen to both blowers
Grit blower discharge valveOpen to both blowers


20.04.b.3. Grit Pumps (also see Section 20.03.b.3.)

The grit pump associated with the first grit bay is placed in REMOTE and pumps the grit slurry continuously. The other two pumps are placed in REMOTE and alternately pump the grit slurry from the second and third grit bays with a recycle timer.

EQUIPMENT STATUS TABLE 20.04.b.3.
Equipment DescriptionStatus
Grit Pump #1, 2, 3HOR handswitch in REMOTE (if first grit channel in operation)
Grit Pumps #4, 5, 6HOR handswitch in REMOTE (if second grit channel in operation)
Grit Pumps #7, 8, 9HOR handswitch in REMOTE (if third grit channel in operation)
Grit Pump suction valvesOpen to all grit pumps
Grit Pump discharge valvesOpen to all grit pumps


20.04.b.4. Grit Classifiers (Also see Section 20.03.b.4.)

The two grit classifiers are placed in REMOTE (only one if one grit chamber is on line), and receive grit from the cyclone degritter(s). The classifiers are designed to start whenever a grit pump starts, and run for a period of time after the grit pump shuts off.

EQUIPMENT STATUS TABLE 20.04.b.4.
Equipment DescriptionStatus
Grit Classifier #1HOR handswitch in REMOTE
Grit Classifier #2HOR handswitch in REMOTE
Grit Classifier #3HOR handswitch in REMOTE
Cyclone degritter suction valveOpen to both degritters
Cyclone degritter discharge valveOpen to both degritters


20.04.c. Alternate Operating Conditions

Blank.

20.04.d. Startup/Shutdown Conditions

20.04.e. Key Control Data and 4 Level Alarm Table

Blank.

20.04.f. Contingency Plans

A Contingency Plan is written to handle an unpredictable occurrence that has a reasonable chance of happening. Most Contingency Plans deal with situations where having a written procedure can help prevent loss of a unit process, handle a process upset or respond to a hazardous situation. The following is a list of Contingency Plans developed for the Grit Removal System. The plans are kept in the Contingency Plan Notebook located in the Operator Laboratory and the Shift Supervisor Office.

20.04.g. Standard Operating Procedures

Standard Operating Procedures are written to handle operator activities performed on a regular but not necessarily daily basis. Most SOPs deal with potentially hazardous activities making it important that a written, step-by-step procedure be available. The following is a list of SOPs developed for the Grit Removal System. The procedures are kept in the SOP Notebook located in the Operator Laboratory and the Shift Supervisor Office.

20.05. Troubleshooting

See Section 75 Maintenance Plan for troubleshooting dealing with the operation of the Grit System which includes the grit chambers, grit blowers, grit pumps, and the grit classifiers.

Refer to Table 20.05.a.1. for troubleshooting the grit blowers.

Refer to Table 20.05.a.2. for troubleshooting the grit pumps and grit chambers.

Refer to Table 20.05.a.3. for troubleshooting the grit classifiers.


TABLE 20.05.a.1. - Grit Blowers
ObservationProbable CauseSolution
Blower(s) not running.LEAD Blower "tripped out". Second blower not in REMOTE position.Place second blower in REMOTE, and investigate LEAD blower malfunction.


TABLE 20.05.a.2. - Grit Pumps/Grit Chambers
ObservationsProbable CauseSolution
Grit Pump(s) not pumping.Pump is plugged.Lock out and clean out pump.
Purge pump sump with compressed air.
Second and third grit bays plugged .Incorrect recycle timer setting.Increase pumping cycle.
First grit bay plugging frequently.Insufficient purging of sump with compressed air.Increase frequency of compressed air purging.
Grit carryover in primary influent.Poor grit removal in grit system.Adjust air in grit chambers.
Increase pumping cycles of pumps in second and third bays.


TABLE 20.05.a.3. - Grit Classifiers
ObservationsProbable CauseSolution
No grit removal evident at classifier.Cyclone degritter(s) plugged.Shut off grit pumps and clear degritters.
Grit pumps may be plugged.See Table 15.05.a.2. for clearing pump(s).
Poor removal in grit chambers.See Table 15.05.s.2. for corrective action.
Grit classifier has stopped.Classifier "tripped out".Reset classifier once.


20.06. Safety

20.06.a. Confined Spaces

20.06.a.1. Grit Chambers

The operator is responsible for reviewing the SOP on Entering the Grit Chambers. A confined space entry form must be filled out and properly signed before entry into the channel. This chamber is continually monitored for combustible gas.

20.07 Records/Sampling

20.07.a. Sampling Schedule

Not used.


<-- Previous Section
Home

Next Section -->