<-- Previous Section | Next Section --> | |
| 15.01 | General Overview |
| 15.02 | Design Criteria |
| 15.03 | Computer Assisted Control Strategies |
| 15.04 | Operating Strategies |
| 15.05 | Troubleshooting |
| 15.06 | Safety |
| 15.07 | Records/Sampling |
The purpose of providing screenings removal is to protect downstream mechanical devices from damage due to the presence of large objects or stringy material. Additionally, the screens will remove debris that collects in the treatment process and sludge facilities and is not amenable to treatment. This material will be removed by bar screens installed in the influent channels. The bar screens will be cleaned mechanically under normal conditions and manually during emergency operation. The mechanical screens will discharge the collected screenings via a chute into a shaftless screw conveyor. The screenings will then be conveyed to a screenings press where they will be compacted. The liquid from the presses will be collected and discharged downstream of the screens.
There are a total of five channels, four channels 4'-0" wide and one channel 6'-0" wide. All the channels were constructed during Phase I. With completion of Phase II, three mechanically cleaned bar screens have been installed in three of the four 4'-0" channels and a manually cleaned bar screen is installed in the 6'-0" channel. An additional mechanically cleaned bar screen will be installed in the remaining 4'-0" channel during Phase III. Each bar screen channel includes a Parshall flume installed downstream of the bar screen to control the water level and flow velocity through the screens. The Parshall flume is also used for flow measurement purposes. The Parshall flumes in the mechanical screen channels is sized at 1'-6" to provide proper upstream velocities and allow accurate flow measurement of flows up to 21 MGD. The Parshall flume in the manual screen channel is sized at 3'-0" to provide proper upstream velocities and allow accurate flow measurement of flows up to 43 MGD.
Specific design features of the screenings facility include:
The design criteria for the Screenings Removal Building Phase II are presented below.
MECHANICALLY CLEANED BAR SCREENS
| Number of Units
| Initial | 3
| Ultimate | 4
| Type | Climber Screen
| Size (width) | 4'-0"
| Bar Spacing | 1/2"
|
| MANUALLY CLEANED BAR SCREENS
| Number of Units | 1
| Type | Static
| Size (width) | 6'-0"
| Bar Spacing | 1"
|
| SCREENINGS CONVEYOR
| Number of Units | 1
| Type | Shaftless Screw
| Size | 12"
|
| SCREENINGS PRESS
| Number of Units | 2
| Type | Hydraulic Ram
| Size | 12"
| Capacity (each) | 30.0 CF/HR
|
| PARSHALL FLUMES
| Mechanical Screen Channels
| Size | 1'-6"
| Minimum Capacity, each | 1.1 MGD
| Design Capacity, each | 15.7 MGD
| Maximum Capacity, each | 21 MGD
| Manual Screen Channel
| Size | 3'-0"
| Minimum Capacity | 1.1 MGD
| Design Capacity, each | 32.6 MGD
| Maximum Capacity | 43 MGD
| | |||||
At the MPWRF, the influent bar screens are mechanically cleaned and the screenings conveyed to a screening press. The operator controls the recycle timer settings and Influent Channel level setpoint using the SCS located in the Marine Park Administration Building. The Parshall flumes located after the bar screens are used to measure influent flow. The PLC calculates the total influent flow and displays the result on the SCS. The operator uses the SCS to monitor alarms and equipment status. The PLC/SCS system also monitors the Screenings Building for combustible gas level and sounds an alarm if an elevated level is detected.
This section tells the operator how to interact with the PLC and the SCS, describes each control loop and describes how and where alarm and equipment status is transmitted.
15.03.b.1. Influent Channel
| Loop Function: | Monitors the level in the channel leading to the bar screens and triggers an alarm if the level gets too high. |
| Instrumentation: | LIT/LE-02000 (Influent channel levels sensor and transmitter) (Located in the influent channel) LSH-02001 (High influent channel level switch) (Located at elevation 42.75' in the influent channel) |
| Alarms: | LAH-02001 (High influent channel alarm) |
| PLC/SCS Function: | Monitor channel high level switch and provide alarm, LAH-02001 Monitor channel level, LI-02000 |
Operation:
| Loop Function: | Turn the bar screen cleaners on and off based on a recycle timer, high channel level ahead of the bar screens or a combination of both. Monitor the bar screen cleaning cycle and sound an alarm in case of a bar screen failure. |
| Instrumentation: | HS-02041, HS-02042, HS-02244
(HAND/OFF/REMOTE [HOR]) (Switches for each screen). (Located at LP-02041, LP-02042, LP-02244) HS-02041, HS-02042, HS-02244 (FORWARD/REVERSE [F/R]) (Switches with return to center position.) (Located at LP-02041, LP-02042, LP-02244) QL-02041, QL-02042, QL-02244 (Barscreen ON light) (Located at local panel LP-02041, LP-02042, LP-02244) QL-02041, QL-02042, QL-02244 (Barscreen FAIL light) (Located at LP-02041, LP-02042, LP-02244) |
| Alarms: | QA-02041, QA-02042, QA-02244 (Barscreen Failure Alarm) |
| PLC/SCS Function: | Monitors all barscreens and provides failure alarm - QA-02041, QA-02042, QA-02244. |
Operation:
Raw influent is mechanically screened by one, two or three barscreens. QL-02041, QL-02042 and QL-02244 indicator lights will be on whenever any of the barscreens are in operation. In the event of a failure of any barscreen, a FAILURE light and horn will be indicated at LP-0204, LP-02042, or LP-02244 and the SCS located at the Operator's Laboratory and the Administration Building.
15.03.b.3. Screenings Conveyor
| Loop Function: | Conveys screenings removed from the mechanically cleaned barscreen to the Screenings Press(es). Monitors conveyor "ON" status and sounds alarms in case of high torque or zero motion. |
| Instrumentation: | HS-03030 (HAND/OFF/REMOTE [HOR] handswitch)
(Located at MCC-02) HS-03030 (START/STOP pushbuttons [SS]) (Located at MCC-02) QL-03030 (Conveyor on light [ON]) (Located at MCC-02) NLH-03030 (Conveyor high torque light [TORQ]) (Located at MCC-02) MLL-03030 (Conveyor no motion light) (Located at MCC-02) HS-03030 (Local auxillary START/STOP pushbuttons [SS]) (Located at the conveyor) HS-03030 (Local emergency pull cord) (Located at the conveyor [EMERG STOP]) |
| Alarms: | NSH-03030 High Torque Switch - Sends a screenings conveyor high torque level alarm to the PLC. Shuts down the screenings conveyor.
MSL-03030 Motion Switch - sends a screenings conveyor no motion alarm to the PLC. |
Operation:
| Loop Function: | Starts the screenings press(es) cycle after a time delay following the start of the screenings conveyor. If operated in the REMOTE position the first press selected will operate as the LEAD press. The other press will serve as the backup, and will start if the LEAD press fails, providing it is also in the REMOTE position. |
| Instrumentation: | HS-03021, HS-03022
(HAND/OFF/REMOTE [HOR] Handswitch) (Located at local panel LP-03021, LP-03022) HS-03021, HS-03022 (START/STOP [SS] pushbuttons) (Located at local panel LP-03021, LP-03022) |
| Alarms: | QA-03021, QA-03022 (provides failure alarm when in REMOTE position)
QA-03021, QA-03022 (determines conveyor failure in REMOTE position and provide alarm [RUN FAIL]) QA-03021, QA-03022 (monitor local press fail from local panel and provide alarm [LOCAL FAIL]) |
| PLC/SCS Functions: | Monitors press ON status.
Monitors screenings conveyor and provide alarm QA-03021, QA-03022 in the event of conveyor failure. Provide press start command. |
Operation:
When selected to REMOTE, a screenings press cycle is started after a set time delay following start of the screenings conveyor. The setpoint of the on delay timer can be viewed through the SCS CRTs. If both presses are selected to REMOTE, the first press selected to REMOTE will function as LEAD with the other press assigned as backup. If the LEAD press fails, the backup press is started if it is in REMOTE.
15.03.b.5. Parshall Flumes
| Loop Function: | Monitors and calculates flume level, calculates level differential, determines flow for each flume, and sums flume flows. |
| Instrumentation: | FI-02051, FI-02052, FI-02053, FI-02254 monitors flume flows
LI-02051, LI-02052, LI-02053, LI-02254 calculates flume level FIT-02051, FIT-02052, FIT-02053, FIT-02254 flume flow indication FQL-02050, sums total flume flows |
| Alarms: | None |
Operation:
Parshall Flumes monitor and measure individual flume flows, and sum total of flows. Flow measurement is indicated in the SCS.
15.03.b.6. Raw Sewage Sampler
| Loop Function: | In FLOW position receives signal from the PLC and initiates sample cycle based on a preset accumulated total. If sampler is set in the TIMER position it ignores the sample signal, and initiates a sample cycle according to the preset timer position. |
| Instrumentation: | FI-02050 (totalizes plant influent flow [TOTAL])
(Plant flow sent to the SCS) HS-02070 (handswitch [TIMER-OFF-FLOW]) (Located at the sampler) HS-02070 (handswitch to manually initiate sample cycle [HAND]) (Located at the sampler) |
| Alarms: | QA-020270 (monitors sampler trouble signal and provides failure alarm) |
| PLC/SCS Functions: | Provides influent flow signal to the sampler and a failure alarm. |
Operation:
The PLC totalizes the influent flow and initiates a sample cycle based on a preset accumulated total. The sample cycle is executed if the sampler is in the FLOW mode. If the sampler is in TIMER mode, the start sample cycle signal is ignored. After the sample cycle is intiated, the totalizer is reset. The preset accumulated total used to initiate a sample cycle can be set through the Sampler Screen at the SCS CRT.
15.03.b.7. Screening Effluent Channel
| Loop Function: | Monitors the screening effluent channel pH. |
| Instrumentation: | AIT/AE-02080 (measures the influent pH)
(Located at the screening effluent channel) |
| Alarms: | AAH-02080, high pH alarm
AAL-02080, low pH alarm |
Operation:
An on-line pH meter monitors the screenings effluent channel pH, and signals low or high pH through the SCS and through the Annunciator panel on LCP-01. High and Low alarm setpoints are adjusted at the Bar Screen page of the SCS CRT.
When selected to REMOTE, a screenings press cycle is started after a set time delay following start of the screenings conveyor. The setpoint and progress of the on delay timer is viewable through the SCS CRTs. If both presses are selected to REMOTE, the first press selected to REMOTE will function as LEAD with the other press assigned as backup. If the LEAD press fails, the backup press is started if it is in REMOTE.
When in HAND mode, the bar screen forward cleaning cycle is started by momentarily placing the F-R handswitch in the FORWARD position. The bar screen is run in reverse as long as the F-R handswitch is held in the REVERSE position. The intent of the reverse switch is to provide momentary reverse action to remove jammed material from the screen. If a bar screen failure is detected, it is indicated by the fail light.
When selected to REMOTE, the conveyor is started after a set time delay following initiation of a bar screen cleaning cycle. It continues to operate after the bar screen stops for a set time delay. The setpoints and progress of both the on delay and off delay timers can be viewed through the SCS CRTs.
When the bar screen, screenings conveyor, and screenings presses are all selected to REMOTE mode, they function together in an automatic sequence. This automatic sequence can be disabled at the Bar Screen page of the SCS. The bar screen cleaning cycle is started by either a high influent channel level ahead of the bar screen, or by a recycle timer. Both the high channel level setpoint and the re-cycle timer preset can be set through the SCS CRTs.
The channel high level float switch activates an alarm to signal that the influent channel is backed up and water is spilling over the weir gate into the manual bar screen channel.
A gas sensor in the screenings area continuously monitors for the presence of combustible gases. When the level of combustible gases reaches the alarm level as set on the alarm module located on LCP-01, the alarm beacons and alarm horns are activated. The alarm horns are silenced by pressing the horn silence buttons. The alarm condition is also monitored by the PLC/SCS system. The alarm condition is acknowledged and reset by the operator at the alarm module. When the level of combustible gas reaches the warning level as set on the alarm module, an input to the PLC is activated to notify the operator of the conditions through the SCS. The warning alarm is automatically cleared when the LEL level drops below the warning trip level.
Note: Normal plant operations will use the PLC and the SCS CRT to enter setpoints, select equipment operating modes and monitor equipment status. Local control of equipment will be covered under section 10.15.c. Alternate Operating Conditions. The influent channel level is continually monitored by the PLC and will sound an alarm if the level increases above 42.75' elevation. The actual influent channel level is indicated on the SCS CRT and at local control panel LCP-01 as a LED bar graph.15.04 Operating Strategies
15.04.a. General Operating Strategy
15.04.b. Normal Operating Conditions
15.04.b.1. Influent Channel (also see Section 15.03.b.1.)
|
| Equipment Description | Status
| LIT/LE-02000 | LEVEL (feet)
| LAH-02001 | HIGH ALARM
| | |
Each bar screen operates on a recycle timer through the SCS/PLC. These timer controls are located on the Bar Screen page of the SCS CRT. From this screen the operator can adjust the off time, and the SCS will monitor all three barscreens and start the unit when the timer counts down to zero. The PLC/SCS will also monitor for failure of either barscreen.
|
| Equipment Description | Status
| Mechanical Bar Screen #1) | Place HS-02041 in REMOTE position
| Mechanical Bar Screen #2) | Place HS-02042 in REMOTE position
| Mechanical Bar Screen #4) | Place HS-02244 in REMOTE position
| | |
The Screenings Conveyor is normally set in the REMOTE position. The conveyor will start after the mechanical bar screen(s) start, according to a preset timer. The PLC/SCS will monitor the conveyor operation and notify the operator in the event of failure.
|
| Equipment Description | Status
| Screenings Conveyor | Place HS-03030 in REMOTE position
| | |
The screenings presses are normally operated in REMOTE position. The first press placed in REMOTE by the operator will become the lead press, while the second one will act as the backup press. The backup press will start in the event the lead press fails. The PLC/SCS will monitor the operation of the presses and notify the operator if the press fails. The press(es) will start after the screenings conveyor starts. The time delay for starting of the presses is preset in the SCS.
|
| Equipment Description | Status
| Screenings Press #1 | Place HS-03021 in REMOTE
| Screenings Press #2 | Place HS-03022 in REMOTE
| | |
There is no special action necessary by the operator in operating the Parshall Flumes, other than assuring the flow measuring devices associated with the flume operation is functioning normally. Flow measurement should occur immediately upon placing a barscreen on line, with flow being directed to that respective Parshall Flume.
|
| Equipment Description | Status
| No equipment is necessary to start. |
| | |
The normal operation of the Raw Sewage Sampler is to run the sampler in the FLOW position. In the FLOW position the sampler initiates a sample cycle based on a preset accumulated total of raw sewage flow (flow proportioned). The raw sewage sampler will send a TROUBLE alarm to the SCS in the event of any malfunction of the sampler. If the sampler is set to the TIMER position a sampling cycle is initiated after a preset time. Any problem with the sampler will activate a TROUBLE signal to the SCS as in the REMOTE position. At any time the operator may switch to MANUAL to initiate a sampling cycle.
|
| Equipment Description | Status
| Raw Sewage Sampler | Place in FLOW position
| | |
There is no special action necessary by the operator to run the Screening Effluent Channel, other than periodically checking the condition of the channel pH meter.
|
| Equipment Description | Status
| No equipment is necessary to start. |
| | |
Blank.
Blank.
A Contingency Plan is written to handle an unpredictable occurrence that has a reasonable chance of happening. Most Contingency Plans deal with situations where having a written procedure can help prevent loss of a unit process, handle a process upset or respond to a hazardous situation. The following is a list of Contingency Plans developed for the Activated Sludge process. The plans are kept in the Contingency Plan Notebook located in the Operator Laboratory and the Shift Supervisor Office.
A Standard Operating Procedure (SOP) is written to handle operator activities performed on a regular but not necessarily daily basis. Most SOPs deal with potentially hazardous activities making it important that a written, step-by-step precedure be available. The following is a list of SOPs developed for the Influent Channel and the Mechanically Cleaned Bar Screens. The procedures are kept in the SOP Notebook located in the Operator Laboratory and the Shift Supervisor Office.
See Section 75 Maintenance Plan for troubleshooting dealing with the operation of the Influent barscreens, screenings conveyor, screenings presses, and Parshall Flume.
Refer to Table 15.05.a.1. for troubleshooting the influent barscreens.
Refer to Table 15.05.a.2. for troubleshooting the screenings conveyor.
Refer to Table 15.05.a.3. for troubleshooting the screenings presses.
TABLE 15.05.a.1. - Influent Channel / Barscreens
|
| Observations | Probable Cause | Solution
| High Influent Channel Alarm | Barscreen plugged | Lock out and clean
| Barscreen "tripped out" | Reset breaker once
| Plant flow high | Bring additional barscreen(s)into service
| Heavy accumulation of debris on barscreen | Barscreen TIMER has incorrect setting | Decrease time OFF
| Barscreen FAILURE alarm | Barscreen failure | Switch to backup barscreen
| | ||||
TABLE 15.05.a.2. - Screenings Conveyor
|
| Observations | Probable Cause | Solution
| Conveyor stopped (no motion light on) | Motor overload | Reset breaker once
| Notify Maintenance
| Conveyor stopped (High TORQUE) | Conveyor stopped due to high torque | Lock out conveyor and remove debris
| Conveyor stopped | EMERG STOP cord pulled | Investigate why cord was pulled
| Debris on conveyor after its stopped | Run time duration set too short | Increase run time setting
| | ||||
TABLE 15.05.a.3. - Screenings Press
|
| Observations | Probable Cause | Solution
| Screenings Press Fail | Press is plugged | Lock out and clean
| | ||
The operator is responsible for reviewing the SOP on Entering the Influent Channel. A confined space entry form must be filled out and properly signed before entry into the channel.
The operator is responsible for reviewing the SOP on Entering the Screenings Effluent Channel. A confined space entry form must be filled out and properly signed before entry into the channel.
Whenever maintenance is being performed on the barscreens they should be locked out electrically, using the standard procedures according to the Lockout/Tagout Policy. Plant flow should be secured to the barscreen using channel gates, if work is to be done in the channel itself. Work in the barscreen channel is considered a confined space, and the appropriate permit should be filled out prior to entry.
Due to the automatic function of this equipment care should be taken whenever working around the mechanical barscreens. Care should also be taken when manually removing debris off the barscreens and ancillary equipment to avoid being cut by sharp objects.
Whenever maintenance is being performed on the Screenings Conveyor it should be locked out electrically, using the standard procedures according to the Lockout/Tagout Policy.
Due to the automatic function of this equipment care should be taken whenever working around the screenings conveyor. Avoid wearing of loose clothing and jewelry while working on the screenings conveyor.
An emergency pull stop cord is provided for the screenings conveyor in both the Screenings Room and the Press Room.
Whenever maintenance is being performed on the screenings presses they should be locked out electrically, using the standard procedures according to the Lockout/Tagout Policy.
Due to the automatic function of this equipment care should be taken whenever working around the screenings press.
Under no circumstances should the press(es) drop chute be left uncovered unless working on it. The hydraulic ram exerts approximately 1450 pounds of pressure, and is capable of severe injury or death.
15.07 Records/Sampling
15.07.a. Sampling Schedule
NAME FREQUENCY TYPE LOCATION |
<-- Previous Section | Next Section --> | |